Memphis Pauses New Data-Center Permits for 135 Days: What Contractors With Pending Work Need to Know
Status: ENACTED. The Memphis City Council adopted Substitute Ordinance No. 5986 on Tuesday, Oct. 20, 2026, and local coverage reports the pause took effect that night. The permanent data-center rules it calls for are not written yet; they're still to be drafted and adopted.
For contractors who build data centers, or who were lining up electrical, mechanical, civil and grading packages for the next one, the City of Memphis just stopped issuing a whole class of approvals. Under Section 10 of Substitute Ordinance No. 5986, no city department, board or employee may "accept for formal filing, process, schedule for hearing, hear, approve, issue, or grant" any new application, permit or land-use approval for the establishment or construction of a new data center inside the city's regulatory jurisdiction. The pause lasts 135 calendar days, unless permanent rules are adopted sooner.
The council passed it 7–4, according to localmemphis.com (ABC24), shortly after an 18-month moratorium failed. Here's what the ordinance text actually says, what it doesn't, and what to do if you have work in the pipeline.
First, clear up the 90-vs-135 confusion
The city's PDF of the ordinance is posted under a file name that says "90-Day Moratorium." The text itself says something else. Section 10 is titled "Temporary One Hundred Thirty-Five (135) Day Pause," and subsection B says the pause "shall terminate at 11:59 p.m. on the one-hundred-thirty-fifth (135th) calendar day" after the effective date. Two separate 90-day clocks explain the file name:
- Mayor Paul Young's Executive Order No. 3-2026, signed Friday, Oct. 9, set up a 90-day expert study of data-center impacts. The ordinance says it is meant to "complement" that order.
- Section 6 of the ordinance gives the Division of Planning and Development (DPD) 90 days to produce proposed code language.
Counting 135 days from Oct. 20, the pause would end at 11:59 p.m. on Thursday, March 4, 2027. That's our own calculation; we didn't find a city-published end date. The ordinance also says the pause can't be extended administratively. Any extension needs a new council vote.
What's covered
Section 10(C) lists the approvals that are frozen for a covered facility:
- zoning changes and other land-use approvals;
- Special Use Permits and other discretionary approvals;
- site-plan, development-plan, grading and other development approvals;
- building permits authorizing construction; and
- anything else the city's Law Division decides is legally subject to the pause.
For the pause, Section 10(F) gives an interim definition of "data center": a building, facility or principal use whose primary purpose is housing and operating networked servers, storage or similar computing equipment, along with its cooling, electrical, backup-generation and mechanical systems. Ordinary server rooms, telecom rooms and network closets that are "accessory and incidental" to another use are excluded. DPD may issue written guidance on applying the definition.
What's not covered
The ordinance is written to avoid knocking out projects that already have legal protection. Section 10(D) says the pause doesn't apply where it would unlawfully impair a vested property right, a previously granted entitlement, or "a legally protected application submitted before the effective date." It expressly doesn't stop:
- work under a valid permit or approval issued before the effective date, for projects commenced before that date, "only to the extent protected by law";
- ordinary repair or maintenance of an existing, lawfully established data center;
- permits needed solely to fix an immediate health, life-safety, fire, structural, environmental or emergency condition;
- work needed to comply with a lawful government order; and
- anything else the Law Division decides must be allowed.
Existing data centers may keep operating (Section 10(E)). For expansions of existing facilities, the ordinance asks DPD to recommend criteria for when an expansion counts as a "material expansion" needing more review. Those criteria are part of the future permanent rules and aren't in force yet.
What the title promises vs. what the text does
This is where a quick read can mislead you. The ordinance's long title talks about prohibiting routine evaporative cooling, requiring closed-loop water systems, a phase-out of carbon-based electricity, and "enforcement, penalties." None of those standards appear as enacted requirements in the body. Sections 1 through 9 are instructions to DPD to evaluate and draft. They cover use classifications, siting near homes, schools and parks, cooling, water and power disclosures, backup generators, and expansion triggers. The permanent framework is expected to move through a separate measure, Ordinance No. 5987, which the ordinance describes as being on second reading. That measure is PROPOSED, not enacted.
We also found no penalty section aimed at contractors. The pause works by binding city staff: permits simply won't be accepted or issued. For a contractor, the practical risk isn't a fine. It's a schedule that slips by four-plus months, or a pre-construction budget spent on a job that can't be permitted.
The dates to put on your calendar
All of these are counted from Oct. 20, 2026, by our calculation:
- About Oct. 30 (10 days): DPD and the Law Division must give the council's Planning and Zoning Committee written guidance. It must cover which applications are paused, how pending applications are treated, and the process for deciding whether vested rights exist. This is the document that tells you where your job stands.
- About Dec. 4 (45 days): DPD must present an analysis of where data centers can be permitted under the current code, the related zoning districts and maps, and its "material regulatory gaps."
- About Jan. 18, 2027 (90 days): DPD must finish proposed code text and start the Memphis and Shelby County Land Use Control Board process. The ordinance says a report or presentation alone doesn't satisfy this deadline.
- About March 4, 2027 (135 days): the pause ends, unless permanent rules take effect earlier or the council votes to extend.
Why this matters to the trades, not just developers
Data-center work around Memphis has been one of the biggest labor stories in the Mid-South this month. CBS News reported that the region has become a hotspot for the facilities, with SpaceXAI operating or building several in and around Memphis, including across the state line in Southaven, Mississippi. Earlier this week, Action News 5 showed hundreds of electricians lining up at the Memphis IBEW hall for data-center jobs.
The pause is a City of Memphis action. It covers approvals "within the regulatory jurisdiction of the City of Memphis." It doesn't reach Southaven or other jurisdictions outside the city. If your crews are staged for a Memphis job that hasn't pulled permits, that work may move later, or move across a line on the map.
What contractors should do this week
- Pull the permit history on every Memphis data-center job you're bidding or staffing. Was a building, grading or site-plan approval issued before Oct. 20? Had work started? Those two facts drive the main exemption in Section 10(D)(1).
- Ask the owner or developer, in writing, how they're treating vested rights. The ordinance leaves that analysis to the Law Division, with written guidance due in about 10 days. Don't assume a job is safe because the owner thinks it is.
- Separate maintenance and life-safety work from new construction. Repair and maintenance of existing facilities, and permits needed to fix immediate safety conditions, are expressly allowed. Scope your change orders so that work isn't caught up with new-build approvals.
- Revisit your bid assumptions. If a job can't get a building permit until spring 2027, pricing, escalation clauses, bonding capacity and crew commitments all change. Talk to your surety early.
- Watch the Planning and Zoning Committee. The 45-day analysis and the 90-day draft text will show where data centers can go in Memphis and what owners will have to disclose. Those rules will decide where the next job can be built.
- Keep your Tennessee and local licensing current regardless. The pause changes when permits issue. It doesn't change who is allowed to do the work.
The bottom line
Memphis didn't ban data centers. Section 10(A) says the pause "shall not be interpreted as a permanent prohibition." What it did was close the permit window for new facilities for up to 135 days, while it writes rules that could decide siting, disclosures and expansions for years. Contractors with permits issued and work underway before Oct. 20 have the strongest footing. Everyone else should read the city's guidance due around Oct. 30 before committing crews.
This article is for general information and isn't legal advice. Verify current requirements with your state licensing board or a licensed attorney.
IQS — connecting construction businesses with state-licensed qualifiers.
Sources
- City of Memphis — Substitute Ordinance No. 5986 (as adopted Oct. 20, 2026) (PDF)
- localmemphis.com (ABC24) — Substitute Ordinance No. 5988: The data center moratorium and what comes next (Oct. 21, 2026)
- Action News 5 — Memphis City Council presses pause on data center construction (Oct. 20, 2026)
- CBS News — Memphis fails to pass 1-year data center moratorium, instead opting for a shorter-term ban (Oct. 22, 2026)
- Action News 5 — Union workers line up for data center jobs (Oct. 19–20, 2026)
- Memphis Flyer — Mayor Paul Young Signs Order for 90-Day Data Center Study (Oct. 9, 2026)
- City of Memphis — Mayor Paul Young orders 90-day data center policy review