    Status: ENACTED (final regulation). The Virginia Board for Contractors has adopted a new section, 18VAC50-22-265, and amended its prohibited-acts list at 18VAC50-22-260. The final regulation was filed September 14, 2026, published in the Virginia Register of Regulations (Vol. 43, Issue 4) on October 5, 2026, and takes effect January 1, 2027.

    The rule implements Chapters 851 and 852 of the 2026 Acts of Assembly, which created §54.1-1117.1 of the Code of Virginia — a statute that, according to the Code's own heading, is also effective January 1, 2027. Together, the statute and regulation set out what every residential solar sale, lease, and power purchase agreement (PPA) must say on paper, and they give the Board a new disciplinary hook when it does not.

    The Board adopted the rule under the §2.2-4006 A 4 a exemption for regulations that conform to new statutory law without agency discretion. The General Assembly made the policy choices; the Board wrote them into its rulebook.

    Who is covered

    Section 54.1-1117.1 defines a "solar installation company" as a licensee that contracts with residential customers to install residential solar energy systems, or to install systems owned by third parties from which customers lease equipment or buy power. The definition excludes third-party owners and financing companies that don't sell or install systems, and it excludes homeowners who self-install.

    A "solar energy system" means a residential system mounted on a residential structure or installed on residential ground.

    The new section does not replace the residential contracting rules already in 18VAC50-22-260; installers still owe those standard contract terms.

    What every solar contract must contain

    Under 18VAC50-22-265(B), any contract for the sale, lease, or PPA of a solar energy system must include the following in at least 10-point font:

    • The name, address, telephone number, email address, and Virginia contractor license number of the solar installation company (and of any third-party lessor).
    • The same identifying details for subcontractors known when the contract is signed. If subs aren't known yet, the installer must provide that information within five business days of contracting with them.
    • The amounts and schedule of progress payments, including a specific statement of the down payment.
    • System design assumptions: size, estimated first-year production, annual degradation, and any energy storage's capacity, maximum power output, and model. Substitutions that differ from the contracted design require customer notice within five business days, and sales proposals using those assumptions must be delivered with the contract.
    • Payment due dates, how invoices arrive, and how to pay. For third-party-owned systems, no payment is due until the system is installed, has permission to operate and interconnection, and is functioning.
    • All one-time or recurring fees (late, removal, UCC refiling, internet, ACH) and, where the installer arranges credit, all loan, dealer, and program fees or points.
    • A description of all performance or production guarantees or estimates.
    • The customer's right to cancel without penalty within five business days of signing.

    The Board's disclosure form

    Subsection C adds a second layer: a set of written disclosures that must be delivered either as a separate signed document before the contract is executed or as a cover sheet to the contract. The regulation requires installers to use a board-provided disclosure form, signed by both the customer and the company. The forms list in the Register identifies it as the Solar Energy System Disclosure Form, A501-27DIS-v1 (eff. 1/2027).

    That form must cover, among other things:

    • Included maintenance and repairs, and costs the customer bears.
    • A required statement that "comparable equipment" may be installed, but only if it would not cut estimated first-year production by more than five percent, shrink the system's AC or DC size, or raise the price.
    • The workmanship warranty covering damage to the home caused by installation.
    • For leases, whether removal costs are included.
    • The basis for any savings estimate, with a copy, including utility rates, assumed rate increases, estimated production, and available excess-energy compensation programs.
    • Who keeps renewable energy credits.
    • Who is responsible for interconnection approval.
    • The five-day cancellation right, including the exact date and time it expires and how to cancel.
    • A required caveat that savings assumptions such as utility rates "may change," and that incentives can be changed or ended by government action.
    • Where a UCC financing statement will be filed, a required warning that a solar loan, lease, or PPA "may affect your ability to sell your home."
    • Lease transferability conditions when the homeowner sells.

    Sale, lease, and PPA specifics

    Subsections D through F split the remaining requirements by transaction type:

    • Sales must list the total cost of the system — equipment, storage, other charges, and reasonable labor and installation estimates. Any price change after signing that comes from equipment substitutions, code or permitting requirements, interconnection, or unforeseen site conditions requires a written change order signed by both parties before the added work is done.
    • Leases must state the term and monthly payment amount, any escalators and the date of the first increase, and the total number of payments and estimated payments over the term.
    • PPAs must state the same term and payment details plus the first-year rates.

    Penalties

    The regulation adds prohibited act No. 38 to 18VAC50-22-260(B): "Failure to comply with the provisions of 18VAC50-22-265." Solar-contract defects now sit in the same disciplinary framework as the Board's other prohibited acts.

    The statute adds a money penalty. Under §54.1-1117.1(H), if the Board finds a willful violation, it shall impose a civil penalty of no more than $2,500 per violation, remitted to the Low-to-Moderate Income Solar Loan and Rebate Fund (§45.2-1916). Prima facie evidence of willfulness may be shown when the Board sends delivery-confirmed notice that a practice violates the chapter and the practice continues.

    What installers should do before January 1, 2027

    1. Rebuild contract templates for sale, lease, and PPA deals against 18VAC50-22-265(B), (D), (E), and (F). Check the 10-point font requirement on every page that carries a required term.
    2. Get the Board's form. Plan to use A501-27DIS-v1 rather than a homegrown disclosure sheet, and build a signature step for both parties into the sales flow.
    3. Align sales proposals with contracts. Design assumptions and savings estimates must match what's in the paperwork, and copies must be delivered with it.
    4. Set up five-business-day workflows for subcontractor notices, substitution notices, and the cancellation window.
    5. Audit third-party partners. Lessors, PPA providers, and lenders feed fee and payment data into your contract — but the license on it is yours.

    Questions about the rule go to the agency contact listed in the Register: Jeannette Galanis, Executive Director, Board for Contractors, contractor@dpor.virginia.gov, (804) 367-2785.

    The bottom line

    Virginia didn't ban any solar product or sales model. It standardized the paperwork. From January 1, 2027, a residential solar deal in the Commonwealth needs a written contract with defined terms, a Board-issued disclosure form signed by both sides, and a five-day exit for the customer. Installers who use the next 11 weeks to rewrite templates will have an easier first quarter than those who learn from a complaint.

    This article is for general information and isn't legal advice. Verify current requirements with your state licensing board or a licensed attorney.

    IQS — connecting construction businesses with state-licensed qualifiers.

    Sources

    Share this article

    Need a licensed qualifier for your business? Request a qualifier match. Hold a license and want to qualify a company? Start here.

    Follow International Qualifier Search for more on Facebook, LinkedIn, YouTube, and Instagram.