California SB 342: A License Lapse Will No Longer Cost Commercial and Public Works Contractors the Whole Job, Starting Jan. 1, 2027
For decades, California has been unusually strict with contractors whose licenses lapse in the middle of a job. Attorneys at Seyfarth Shaw call the consequences "draconian." On Jan. 1, 2027, that rule changes for a large share of commercial and public work. Senate Bill 342 is now ENACTED: Gov. Gavin Newsom signed it, and it was chaptered on Sept. 30, 2026, as Chapter 967, Statutes of 2026. It amends Business and Professions Code § 7031, the provision that has let owners refuse payment, and even claw back every dollar already paid, when a contractor wasn't licensed "at all times" during a project.
The relief is real, but it has limits. Here's what changed, who it covers, what stays the same, and what to do before New Year's Day.
The rule that's on the books until Dec. 31
Under § 7031 as it reads today, a contractor can't sue to collect for work that requires a license unless it was "a duly licensed contractor at all times during the performance" of the contract. Subdivision (b) lets anyone who used an unlicensed contractor sue to recover all compensation paid. The main safety valve is subdivision (e), "substantial compliance." To use it, a contractor must prove at an evidentiary hearing that it had been licensed before the work began, acted reasonably and in good faith to stay licensed, and moved promptly to fix the problem once it found out.
In practice, a renewal that slips by a few weeks, or a qualifier who leaves without a timely replacement, could put an entire contract balance at risk, along with everything already collected. The statute's penalty has nothing to do with the quality of the work.
A real case: the $18 million paperwork problem
Judicial Council of California v. Jacobs Facilities, Inc. (Cal. Ct. App., 1st Dist., filed Aug. 20, 2015) shows how far that exposure can reach. According to the court's opinion:
- In April 2006, Jacobs Facilities signed a three-year contract to maintain and repair 121 judicial branch buildings in Southern California. It held a Class B license when it started.
- During a corporate reorganization, the employees doing the work moved to a sister company, Jacobs Project Management Co. The qualifying individual on the Facilities license, Scott McCallister, withdrew on Aug. 12, 2008. Three days later the new company received its own Class B license with McCallister as its qualifier.
- Facilities never designated a replacement qualifier. Its license was suspended and then expired by operation of law in November 2008. Facilities stayed the named contractor on the job for nearly another year, until the parties signed an assignment in November 2009.
- The Judicial Council sued under § 7031(b) to recover what it had paid Facilities. The jury found that amount was $18,331,911.
A jury sided with the Jacobs companies, but the Court of Appeal reversed. It held that Facilities violated the license law by continuing as the contracting party after its license expired, and sent the case back for the substantial-compliance hearing that had never been held. The opinion notes there was no evidence the work itself was deficient.
That one missing qualifier filing exposed an eight-figure contract to a disgorgement claim. SB 342 is aimed at outcomes like this.
What SB 342 changes on Jan. 1, 2027
According to the Legislative Counsel's digest of the chaptered bill, SB 342 creates a separate track for contracts on specified projects. Two things change on those projects:
1. Contractors can be paid for their licensed work. A contractor may sue for compensation if it "was a duly licensed contractor at the time the contract was executed and during the portion of the performance of the contract for which compensation is sought." A lapse partway through no longer wipes out payment for the licensed portions of the job.
2. Clawbacks are limited to the unlicensed period. An owner or upstream party can recover only "the portion of compensation paid to the unlicensed contractor for work performed during the time in which the contractor was unlicensed," not every dollar paid under the contract.
Which projects are covered
Based on the chaptered bill as summarized by the Legislative Counsel and by attorneys at Seyfarth Shaw, Finch, Thornton & Baird, and Mahrouyan Law, the new track applies to contracts for:
- public works of improvement;
- commercial construction projects;
- institutional construction projects;
- construction of a common interest development, if a tenant or resident isn't a party to the contract; and
- multifamily residential projects of four or more units, again only if a tenant or resident isn't a party.
What isn't covered
Single-family homes, home improvement contracts and other residential work outside those categories stay under the old all-or-nothing rule. For residential and remodeling contractors, a lapse is as dangerous on Jan. 1 as it is today.
What stays the same, even on covered projects
Several parts of § 7031 are untouched, and they matter:
- You must be licensed when you sign. The new path requires a valid license on the day the contract is executed. It doesn't help anyone who was never licensed. Subdivision (e) still bars the substantial-compliance doctrine for a person who "has never been a duly licensed contractor in this state."
- Security interests are still at risk. Section 7031(c), which makes a security interest unenforceable if the contractor wasn't licensed "at all times," was not amended. Finch, Thornton & Baird warn that mechanics' lien rights can still be lost after a lapse. Seyfarth Shaw raises the same concern.
- Criminal and administrative exposure hasn't changed. Under § 7028, contracting without a license is a misdemeanor, punishable on a first conviction by a fine of up to $5,000, up to six months in county jail, or both. Repeat convictions carry stiffer mandatory penalties.
- The qualifier clock still runs. Under § 7068.2, when a responsible managing officer or employee leaves, the licensee has 90 days to notify the registrar and 90 days to replace them. If either deadline is missed, the license or classification is automatically suspended.
The open question: projects already underway
The bill doesn't say whether the new rules apply only to contracts signed on or after Jan. 1, 2027, or also to work that's already in progress. Seyfarth Shaw's Heather Frisch expects that gap to produce "early litigation." Finch, Thornton & Baird say the changes don't apply to projects completed before Jan. 1, but that it's an open question how courts will treat projects that start before that date and finish after it. Mahrouyan Law advises against assuming the new framework reaches back to earlier lapses. If you're in a dispute over a pre-2027 lapse, don't count on SB 342 until a court rules.
Who carried the bill
SB 342 was authored by Sen. Thomas Umberg, whose district includes several Orange County communities. Hearing records on CalMatters' Digital Democracy show it went through Senate Business, Professions and Economic Development (Jan. 12, 2026), Senate Judiciary (Jan. 13), the Senate floor (Jan. 26) and Assembly Business and Professions (June 30 and Aug. 25), followed by Assembly and Senate floor sessions on Aug. 30.
What California contractors should do now
- Classify your active contracts. Mark each job as covered (public works, commercial, institutional, a CID or 4+ unit multifamily with no tenant or resident party) or not covered. Residential and home improvement jobs stay under the strict rule.
- Put every renewal on a calendar. That means the license, the bond and workers' compensation. Remember § 7141.5: the registrar must grant a retroactive renewal if a complete renewal application and fees are delivered or postmarked within 90 days of expiration. Treat that as a backstop, not a plan.
- Watch your qualifier. If your RMO or RME is leaving, line up the replacement application before their last day. That's exactly where the Jacobs problem started.
- Pull a verified license history. If a dispute is brewing, get a certificate of licensure from CSLB covering the full performance period. Under § 7031(d), the burden of proving licensure is on the licensee.
- Document work by date. On covered projects, recovery will turn on what work was done while you were licensed. Pay applications, daily logs and invoices that line up by date will matter more than ever.
- Don't rely on lien rights after a lapse. Section 7031(c) hasn't changed. Talk to construction counsel before you record anything.
If your California business needs a licensed RMO or RME, or you hold a license that could qualify a company, IQS connects the two.
This article is for general information and isn't legal advice. Verify current requirements with your state licensing board or a licensed attorney.
IQS — connecting construction businesses with state-licensed qualifiers.
Sources
- SB 342: Contractors: unlicensed work — chaptered Sept. 30, 2026 (Ch. 967), Legislative Counsel's digest and hearing history (CalMatters Digital Democracy)
- SB 342 bill text — California Legislative Information
- Seyfarth Shaw (via Legal 500), "California Contractors Get A Much-Needed Break: SB 342…" (Oct. 11, 2026)
- Finch, Thornton & Baird, "SB 342 Limits Licensing-Lapse Forfeitures Under Section 7031" (Oct. 2, 2026)
- Mahrouyan Law, "California Enacts SB 342" (Oct. 1, 2026)
- Judicial Council of California v. Jacobs Facilities, Inc., No. A140890 (Cal. Ct. App. Aug. 20, 2015) (PDF)
- CSLB 2026 California Contractors License Law & Reference Book (§§ 7028, 7031, 7068.1, 7068.2, 7141.5) (PDF)