    Prices Moved After the Contract Was Signed? In Maine, the Fix Goes Through a Signed Change Order

    IQS Editorial Team
    October 21, 2026
    8 min read

    Anyone pricing jobs this fall knows the dilemma: hold the number you quoted and eat the increase, or ask the homeowner for more.

    That argument has been all over contractor feeds this week. One X post on Oct. 19 called a bid "a forecast." It claimed steel is up 50% in a year, copper is near a record and freight moves week to week. If a contractor's price is held for 30 days and the escalation clause is silent, the post argued, "someone is carrying a free option." A reply to a widely shared housing-price post on Oct. 20 put it more bluntly: tariffs and diesel are pushing contractor costs "through the roof." In Maine the debate has a local angle. On Oct. 16, Sen. Susan Collins's campaign account posted that tariff exemptions for road salt and cement, which she had pressed the administration for, came through within days. That post drew 134 replies.

    Here's the data, and how Maine law shapes a residential contractor's options.

    The squeeze, in numbers

    • Input costs vs. bid prices. According to AGC's Oct. 16 Data DIGest, input prices for new nonresidential construction rose 11.9% from September 2025 to September 2026, the biggest jump in four years. What contractors say they would charge for new nonresidential buildings rose only 5.4%. Input costs are rising more than twice as fast as selling prices.
    • What's driving it. The same report puts diesel up 115% and steel mill products up 28%. It attributes the metals increases to tariffs of up to 50%.
    • Projects are slipping. In an AGC survey from July and August (results released Sept. 3), 55% of respondents said projects had been canceled, postponed or scaled back in the past six months, and one-third blamed rising costs. In AGC's Sept. 10 analysis, chief economist Ken Simonson described firms as "squeezed by tariff- and war-induced materials cost increases."
    • Maine jobs. BLS data shows Maine construction employment at 35,100 in September 2026, down from 35,500 a year earlier.
    • Lumber relief isn't coming yet. The cement exemption doesn't extend to lumber. Collins's Sept. 8 statement said significant tariffs, "including those on forest products," remain in effect.

    These are national, mostly nonresidential figures, but anyone pricing framing, roofing, wire or fuel has felt the same pressure.

    Maine's rules for home construction contracts

    Maine doesn't license general contractors. The Attorney General's office says plainly that general contractors, and trades such as roofing and framing, "are not licensed or regulated" in Maine. Plumbers and electricians are licensed. What does apply to most residential work is the Home Construction Contracts Act, 10 M.R.S. §§ 1486–1490.

    Who it covers. Under § 1486, a "home construction contract" is a contract to build, remodel or repair a residence. That includes electrical, plumbing and heating work, carpeting, window replacement and other nonstructural work. A "residence" is a dwelling with three or fewer living units. Commercial buildings are excluded.

    The $3,000 line. Under § 1487, any home construction contract for more than $3,000 in materials or labor must be in writing and signed by both parties. Each party must get a copy before work starts.

    The price clause. The contract must state "the total contract price, including all costs to be incurred in the proper performance of the work." Alternatively, if the work is priced on a "cost-plus" formula, it must state the agreed-upon price and an estimate of the cost of labor and materials (§ 1487(4)).

    The deposit cap. The initial down payment is limited to no more than one-third of the total contract price (§ 1487(5)). "Down payment" means all payments made before or when the contract is signed (§ 1486(2)).

    Dates can move, the price can't on its own. The estimated start and completion dates may change for circumstances beyond the contractor's control, and the statute names "the unavailability of building materials" (§ 1487(3)). That language covers dates only. The price provisions are different.

    Price changes need a change order. Every covered contract must include this statement: "Any alteration or deviation from the above contractual specifications that results in a revision of the contract price will be executed only upon the parties entering into a written change order" (§ 1487(9)). Section 1488 adds the mechanics. The change order must be in writing, must detail all the changes that revise the price, must state both the previous contract price and the revised price, and must be signed by both parties.

    Opting out takes informed consent. Under § 1489, the parties can exempt themselves from these requirements only if the contractor specifically informs the homeowner of their rights under the chapter and both then agree to a contract or change order without the required parts.

    Penalties. Under § 1490, a violation is prima facie evidence of a violation of Maine's Unfair Trade Practices Act. It's also a civil violation carrying a forfeiture of $100 to $1,000 per violation, with a two-year limit on bringing that action. A contractor can avoid the civil penalty by proving the violation was an unintentional, bona fide error made despite reasonable procedures.

    A practical playbook for volatile prices

    This is general information, not legal advice. The specific wording of any price-adjustment term in a Maine home contract is a question for a Maine attorney.

    1. Pick your pricing model on purpose. The statute recognizes two: a total contract price, or a cost-plus formula with an agreed price and an estimate of labor and materials. If you can't stand behind a fixed number on a long job, talk with your attorney about whether cost-plus fits that project.
    2. Keep the exposure window short before signing. A short validity period on proposals, with a requote when it runs out, limits the "free option" problem.
    3. Describe materials precisely. The contract needs "a general description of the work and materials to be used" (§ 1487(6)). The more specific the description, the easier it is to show that a later substitution or price revision really is a change.
    4. Never just add an increase to the invoice. In Maine, a price revision on covered work goes through a written change order that states the old price and the new price and that both of you sign. Keep the dated supplier quote that justifies the change in the job file.
    5. Remember the one-third cap when you think about buying materials early. You can't simply collect a larger deposit to lock in prices. The statute's exemption route requires the homeowner's informed, written agreement, and the AG's office warns homeowners to understand what they're giving up.
    6. Start from the state's templates. The AG's office publishes a model home construction contract, a required addendum and a model change order that it says meet the statute's requirements.

    The takeaway

    The held-bid debate is about who carries the risk between quote and invoice. In Maine, once there's a covered contract, the price changes only through a signed change order showing both numbers. Plan for that before you send the proposal.

    This article is for general information and isn't legal advice. Verify current requirements with your state licensing board or a licensed attorney.

    IQS — connecting construction businesses with state-licensed qualifiers.

    Sources