    The conversation

    On Oct. 30, an estimator for a contractor that does Division 7 and 9 work (thermal and moisture protection, and finishes) posted to r/StructuralEngineering. The construction documents left the gauge of the wind-load-bearing exterior studs unspecified. The cold-formed framing was a delegated-design scope, so the firm priced the gauge it usually runs, 18. Then the delegated design engineer called for 16 and, according to the post, wouldn't share the calculations. The job is now losing money. Hard Hat Report picked up the thread the next day.

    Anyone who has bid exterior framing on a commercial job knows this story. It isn't really about steel. It's about who sets the design criteria, who's allowed to rely on them, and what your proposal said when the numbers were missing.

    What "delegated design" means on paper

    Under the standard contract forms, delegated design follows a defined process.

    AIA A201-2017, § 3.12.10.1. If the contract documents specifically require the contractor to provide professional design services or certifications, "the Owner and the Architect will specify all performance and design criteria that such services must satisfy." The contractor is entitled to rely on the adequacy and accuracy of those criteria. The contractor must have the work done by a properly licensed design professional, whose signature and seal go on the drawings, calculations, specifications, certifications and shop drawings that professional prepares. (Text as quoted by Peckar & Abramson attorneys in a ConsensusDocs article.)

    ConsensusDocs 200, § 3.15 goes further. The owner must specify all performance and design criteria, and the constructor "shall not be responsible for the adequacy" of them.

    The building code (IBC § 107.3.4.1, deferred submittals). Deferring a submittal needs the building official's prior approval. The registered design professional in responsible charge lists the deferred items on the construction documents and reviews the delegated submittal for general conformance before forwarding it. Deferred items can't be installed until the building official approves them (UpCodes text).

    Those sections give the specialty contractor two practical points. First, the criteria, meaning the wind pressure and the deflection limit, are supposed to come from the design team. Second, the calculations behind the stamped design are part of the sealed submittal. Under A201, the seal belongs on the calculations too.

    Why the gauge moved

    On a curtain wall (non-load-bearing exterior) stud, gauge follows the criteria. ClarkDietrich's structural stud guide lays out the inputs:

    • Load. Curtain-wall studs must resist the highest lateral load, wind or seismic, that the code requires for the site. ClarkDietrich says wind pressures are usually in the "general notes" on the structural drawings, and that the engineer of record or the specialty engineer must provide the design loads.
    • Load basis. Since IBC 2012 and ASCE 7-10, design wind pressures are strength-level (LRFD). ClarkDietrich's span tables are service-level (ASD), so you multiply the code pressure by 0.6 before entering them. A 25 psf design pressure becomes 15 psf in the table.
    • Deflection, set by the cladding. ClarkDietrich's typical limits are L/240 for siding or EIFS, L/360 for stucco, and L/600 or L/720 for brick or stone. On a 20-foot wall, L/240 allows 1 inch of deflection.
    • The steel itself. In ClarkDietrich's line, an 18-gauge stud is 43 mils of 33 ksi steel. A 16-gauge stud is 54 mils of 50 ksi steel. That's about 26% thicker (our calculation), and stronger steel besides.

    Change any one input and the gauge can change. A higher pressure at a corner zone, a stiffer deflection limit for a brick veneer or a taller span can each do it. ClarkDietrich also notes that adding bridging doesn't reduce deflection. Only a heavier member or an intermediate support does. When the criteria aren't on the drawings, an estimator who prices "our usual 18" is guessing at an engineering decision someone else will make.

    Who pays? What the documents point to

    This is general information, not a legal opinion on any one contract. But the forms point the same way:

    • If the construction documents never stated the wind pressure or deflection criteria, A201 § 3.12.10.1 says the owner and architect "will specify all" of them. That's where a change request starts.
    • If the criteria were stated and the estimator didn't run them, the gauge change is probably the contractor's own estimating risk.
    • A delegated engineer who won't release the calculations is at odds with a contract that requires a seal on calculations. Asking for the sealed calculations as a submittal isn't a favor. It's the deliverable.

    The Peckar & Abramson attorneys put the choice bluntly. Specialty contractors should either accept delegated-design risk knowingly and price it, or use contract language that limits it.

    Our take: how to bid delegated framing without donating your margin

    This section is commentary based on the documents above.

    1. Write your assumptions into the proposal. List the design wind pressure you priced (and whether it's ASD or LRFD), the deflection limit, the stud depth, the spacing and the gauge. One line each.
    2. Exclude the upgrade. Add a sentence such as: "Member sizes, gauges and connections beyond the stated assumptions will be priced as a change once sealed calculations are provided."
    3. RFI the missing numbers before bid day. If the general notes don't state wind pressures or the cladding deflection limit, ask in writing and keep the response.
    4. Make sealed calculations a submittal item, due before steel is ordered, not after.
    5. Hire, or line up, your delegated engineer before you bid. A quick conversation about likely gauges at the corner zones costs less than a 16-gauge surprise.
    6. Remember the inspector. Under IBC § 107.3.4.1, deferred items can't be installed until the building official approves them. Schedule the submittal so the sealed design arrives with time to spare.

    The thread's lesson is short. In delegated design, the person who sets the numbers controls the margin. Get the numbers in writing, and put your assumptions in writing too.

    This article is for general information and isn't legal advice. Verify current requirements with your state licensing board or a licensed attorney.

    IQS — connecting construction businesses with state-licensed qualifiers.

    Sources

    Share this article

    Need a licensed qualifier for your business? Request a qualifier match. Hold a license and want to qualify a company? Start here.

    Follow International Qualifier Search for more on Facebook, LinkedIn, YouTube, and Instagram.